Please find below the meeting minutes of the Supervisory Committee Meeting held on 17 September. - Next online project meeting 26/9.
1. Progress Report:
Review meeting well done without any major concerns; JP to distribute the official report when received from EC PO
1. Upcoming Milestones, Deliverables and Actions: see overview here [?pptx icon] RELAX-DN online Part A reporting by 28 Feb 2025.pptx<https://chalmers.sharepoint.com/:p:/r/sites/ChalmersRELAX-DN_all/Shared%20Documents/General/03%20Reporting/RELAX-DN%20online%20Part%20A%20reporting%20by%2028%20Feb%202025.pptx?d=w63e03e11cd3a4e1886814d55799d3d24&csf=1&web=1&e=HPFjlp>
2. Dissemination and outreach activities according to GA: JP to check how it was phrased re. "two press releases per year"; scientific online magazine 'Conversation' (Deepak to lead the process as he's used it) ACTION: all to think about their already planned activities/events/talks/presentations and how they could be framed into the RELAX context
3. Procedures for Student Progress Review: 5 mins closed session with each student resp. main and co-supervisor; non-conflicting feedback to all students by remaining supervisors; review panel consists of all supervisors but without DC representatives
1. Seminars: two random papers per seminar; Jacob to schedule series
1. Zenodo to be used because of open access
2. Next Training days will be at Chalmers: PT to create a doodle for April 2025 to de-couple from DEBS
* DEBS will be hosted by Marina and Vincenzo 10-13 June 2025 in Gothenburg https://2025.debs.org/; 10 June workshop day at DEBS = part of RELAX training; DEBS Tutorials could be organized as part of RELAX-DN training school; PT/Marina/Vincenzo to create conference tutorials
* Committee: one member from each site: PT/JP from Chalmers; other still to be assigned
* Theme: to be developed by DC reps
3. Industrial Partners
* Agreement: JP to send reminder to all PIs to get agreements signed
* Changes: discussions with Ass Partners as needed; justifications on a case-by-case basis; deviations must be reported to EC PO
* Planning: on an individual basis and when best suitable in the training plan
1. Common projects: supervisors to look out for possibilities; challenge how to build the network community and collaborate across the individual research projects -
* PMT to follow up in 2-3 months; seen opportunity rather than coercion
* Blog posts to share the individual research for identifying potential collaborations;
* maybe smaller pilots for promising ideas such as joined publications or shared position papers?
Visits
AOB: Jacob/Marco to be replaced as DC representatives at SB meetings
Thanks and best regards,
Jacqueline and Philippas
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.chalmers.se/pipermail/relax-dn-pi/attachments/20240918/704fbcdf/attachment-0001.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image001.png
Type: image/png
Size: 432 bytes
Desc: image001.png
URL: <http://lists.chalmers.se/pipermail/relax-dn-pi/attachments/20240918/704fbcdf/attachment-0001.png>
More information about the Relax-dn-pi
mailing list